• Llanddulas Pier, North Wales was systematically reduced with careful planning around low tide, monitoring soft sand conditions, and consideration for local wildlife and environment.

  • This very challenging project at Blackpool Sands involved the strip out of the building, temporary works to allow the remote demolition and removal of the top floor infrastructure, the dismantling of a substantial concrete link bridge and access stairway.

  • The project brief was to demolish an 18-storey building inclusive of all services located on the roof. The method implemented was floor-by-floor demolition with demolition specific 360 machines and attachments, along with light weight skid steers, the machinery sited on each floor working down to the next floor down to ground level.